Rescue officials say 14 people were also injured in incident, one of whom remains under treatment at hospital
Rescue personnel and volunteers search for victims in the rubble of a collapsed under-construction building in Karachi on November 25, 2026. Photo: AFP
KARACHI:
The death toll from the collapse of an under-construction six-storey building in Karachi’s Administrative Society rose to seven on Friday after three more bodies were recovered from the rubble, rescue officials said.
The six-storey under-construction building collapsed on November 25, killing four people and injuring 14 others. Around 30 labourers were reportedly inside when the structure gave way. Initial findings indicated that the building had been approved for a basement, ground floor and one additional storey, but six extra floors had allegedly been constructed. Police detained six people, including the contractor and the structural engineer, while the SBCA suspended six officials. The authorities also sealed 12 other under-construction buildings in the area.
According to the rescue official, the rescue operation had been underway for 45 hours, with heavy machinery being used to remove debris and locate those feared trapped under the rubble.
Rescue officials said 14 people had also been injured in the incident, one of whom remained under treatment at a hospital. The bodies recovered from the rubble were transported to Jinnah Postgraduate Medical Centre (JPMC) in ambulances for medico-legal formalities.
A day earlier, Sindh Chief Minister Murad Ali Shah ordered the removal of senior officials, including Waseem Shamshad, who served as both Sindh Building Control Authority (SBCA) director general and local government secretary, and the suspension of 16 SBCA officers following a deadly building collapse.
“I will not tolerate any incident that results in the loss of human life or causes suffering to people,” he said, directing the relevant authorities to take immediate action against those responsible.
The chief minister also ordered the removal of Deputy Commissioner East Nasrullah Abbasi. On the advice of the home minister, he directed the immediate removal of SSP East Zubair Sheikh over alleged negligence.
Turning to those directly linked to the construction, the chief minister directed the police to immediately arrest the building owner, Salman Tahir, and the builder, Zeeshan.
He also instructed the chief secretary to include the building’s architect and structural engineer in the investigation to establish whether the construction had complied with approved plans, building regulations and safety standards.
Court vacates interim stay in collapsed under-construction building case
A civil court vacated an interim stay order concerning the collapsed building, after the plaintiff failed to advance arguments on his application for an interim injunction despite being given several opportunities.
The Senior Civil Judge (South) was hearing a suit filed by the building owner against the SBCA.
During the hearing, an associate of the plaintiff’s counsel appeared before the court and sought an extension of the interim injunction. However, the court rejected the request and vacated the interim order relating to the building. In its observations, the court noted that the plaintiff had filed a suit seeking a declaration and an injunction on August 1.
Read: Approved for two floors, built seven – then came the collapse
On August 4, the court directed the parties to maintain the status quo until the next hearing. However, the plaintiff subsequently failed to present arguments on his application for an interim injunction despite being afforded multiple opportunities.
The court further noted that on October 12, the plaintiff had been warned that appropriate proceedings could be initiated if arguments were not presented.
The judge also issued notices to the parties on the SBCA’s application seeking dismissal of the suit and directed them to submit their replies by December 4. The hearing of the civil suit was adjourned until December 4.
Four suspects remanded for five days
A judicial magistrate (South) remanded four suspects in police custody for five days in a case about the deaths caused by the collapse of an under-construction building in Karachi.
Police produced the four arrested suspects, identified as Yar Muhammad, Afzal Khan, Munir Akram and Saad Tahir, before the court. The suspects included relatives of the contractor, while the building’s owner and contractor were not produced before the court.
The investigating officer (IO) informed the court that permission had been granted for the construction of a ground-plus-one-storey building, but six storeys were being constructed in violation of the approved plan.
The court asked whether any steps had been taken to obtain forensic and other reports.
The IO said he had been assigned the investigation the previous night and had yet to begin the probe, requesting the court to grant physical remand of the suspects.
The defence counsel argued that it was unclear why his clients had been arrested and produced before the court, questioning the grounds for their arrest over the illegal construction.
One of the suspects told the court that they had merely been working at the site when they were arrested.
“We are neither the owners nor the contractors. Why have we been arrested? Our role in the building collapse should be clarified,” the suspect said.
“Is being someone’s brother also a crime? My brother fled, and I was arrested,” he added.
The defence counsel asked the IO how many people had been arrested in connection with illegal construction elsewhere, arguing that action was being taken only against labourers.
The defence maintained that labourers working at the site had lost their lives, while no action was being taken against those primarily responsible for the incident.
Read more: CM Murad orders removal of SBCA chief, suspension of 16 officers over Karachi building collapse
The counsel also questioned whether any officials of the SBCA had been arrested.
One of the suspects maintained that they had been produced before the court as though they were the building’s owners.
The court remarked that arresting the owner would help establish who had been receiving money.
It also questioned why SBCA officials, the building’s owner and the contractor had not been nominated.
The public prosecutor argued that the case involved a serious offence and requested the court to grant physical remand of the suspects, maintaining that those against whom no evidence was found would be released.
The court remarked that SBCA officials responsible for the incident should also be arrested.
It subsequently remanded the four suspects in police custody for five days and directed the IO to submit a progress report at the next hearing.
Background
The building stood on a 600-square-yard plot and had been approved in March 2026 for a basement, ground floor and one additional storey. However, six extra floors were allegedly added, turning it into a residential complex comprising more than 20 flats. The building had reached seven storeys despite the approved plan, with construction of a seventh floor reportedly under way for a penthouse when it collapsed.
Around 30 labourers were reportedly inside the building at the time of the collapse. Rescue teams pulled 13 injured workers from the rubble and recovered three bodies. A local resident told The Express Tribune that construction of six floors had been completed on Tuesday and work had then begun on the seventh. He also said boring work was underway to extract underground water and that residents had experienced intense ground vibrations.
Police detained five people, including the contractor responsible for the construction, for questioning. Meanwhile, the collapse prompted a wider crackdown on suspected illegal construction in the neighbourhood. The Sindh Building Control Authority sealed 12 other under-construction buildings in Administrative Society and began examining their ownership records, construction documents and approvals to determine whether they complied with building regulations.